Jump to the main content block
Division of Construction & Maintenance
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

1/14 ~3/13 Research and Development Building sewerage common dust project

Subject:Research and Development Building sewerage common dust project construction schedule announcement.
Caption:
1. This project (sewerage common dust project) is scheduled from January 14, 2020 (Tuesday) ~ March 13, 2020 (Friday).
2. Constructing area will be the Research and Development Building Space (Detailed in the following drawing). During the constructing period, noise will be caused due to the equipment and machines, non-relevant vehicles and personnel are not allowed to enter near the constructing area.
3. During construction, non-related personnel or vehicles should not be close to the surrounding area of the construction. To ensure the safety of personnel, the construction area is isolated by safety cones or warning tapes. Sorry for any inconvenience caused. The construction will be postponed when encounter rainy days or any school's major activities. Thanks for your cooperation.
Contractor:Tzung Jiun Ltd. Mr. Jeng 0921-980629
Division of Construction & Maintenance:Mr. Shie 03-5715131#75601
Security: Campus security 03-5714769 Campus direct dial 33333