2020/11/21~2021/4/30 College of Technology Management,TSMC Building 1-8F Toilets Repairment Project

■ This Project will start from 2020/11/21 (Sat) to 2021/4/30 (Fri),within 140 days. The date can be postponed due to weather factors.
■ The construction site is shown as the following map. Irrelevant staff and vehicles please stay away.
■ We apologize for the inconvenience, for example, noises, dust, and detours that the construction causes. Thank you for your cooperation.

Contractor:Tiangang Construction Company Ltd. (02) 85216185
Site Manager:Mr. Huang 0915-862-036
Construction Supervisor:Huang Junxian Architects 03-5166133
Contact:Hai-Ching Chou, Division of Construction and Maintenance 03-5731341 (Campus phone:31341)
Emergency Contact for Campus Safety:Campus Security Office 03-5714769 (Campus phone:33333)