Construction Schedule: From Tuesday, October 27, 2026, until Sunday, November 28, 2027. (Construction will primarily take place during weekends and daytime hours. We kindly ask for your understanding should special construction procedures require work to be conducted during class sessions.)
Affected Areas (Including Surroundings):
North Campus Main Substation MOF2、Nuclear Reactor Building (THOR)、Radioisotope Laboratory、Accelerator Building、High-energy Optics and Electronics (HOPE) Laboratory、Engineering and System Science New Building、Waste-Water Treatment Plant, South Campus、Cheng-Yi-Ching Dormitories Substation、Dormitory Thing、Dormitory Hsin、Dormitory Yi、Dormitory Hung、Dormitory Shiue、Dormitory Ru、Dormitory Li、Dormitory Cheng、Dormitory Hua、Shui Mu Student Center、Feng Yun Building、Dormitory Shuo、Dormitory Jen-Shyr、Dormitory Shinn、Mong Man Wai Building (Student Union)、Track and Field、Dr. Mei Memorial Garden、Gymnasium、Swimming Pool、Volleyball Field、Physics Building、Table Tennis Arena、C. L. Liu Building、Alumni Gymnasium、Engineering Building III、Waste-Water Treatment Plant, North Campus、Materials Science and Technology Building、Materials Science Laboratory、Baseball Field、Basketball Field、Alloy Laboratory、Indoor Tennis Courts、Outdoor Tennis Courts、Delta Hall.
Purpose of Work:
To optimize power efficiency and ensure a more stable electrical infrastructure, the Construction and Maintenance Division is initiating the "Main Campus High-Voltage ABCD Loop & Electromechanical Center Power Upgrades." This project involves extensive underground conduit maintenance and equipment replacement. Please expect heavy machinery and construction vehicles throughout the campus.
Key Safety & Impact Reminders:
Noise & Vibration Alert: Operations involving pavement cutting, manhole access, conduit cleaning, installation of cable trays/hangers, core drilling, equipment hoisting, and cable pulling will generate unavoidable mechanical noise and vibrations. We sincerely apologize for any inconvenience caused.
Traffic & Pedestrian Safety: Work zones will be secured with warning signs or fencing. Construction vehicles may be stationed near manholes. Please slow down when passing work sites and follow the guidance of on-site safety personnel.
Environmental Care: We will strictly supervise contractors to ensure the immediate cleanup of dust and debris, minimizing any impact on the campus environment.
Construction and Maintenance Division
Contact Information:
Power System Liaison: Mr. Hsu (Ext. 35253)
Email: myhsu@mx.nthu.edu.tw
27 October 2026