Jump to the main content block
Division of Construction & Maintenance
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

5/6~6/13 Motorcycle Parking Ramp to Hall of Fame Gas pipe update.

 

  • This construction starts from 2024/02/15(Thu.) to 2024/06/13(Sat.).
  • Each stage schedule Orange line 5/6 (Mon.) ~ 5/12(Sun.), Red line 5/13 (Mon.) ~ 6/13 (Thu.) Early completion will lead to subsequent phases.
  • Construction areas are shown on the maps below. Due to the safety reason, non-construction personnel please keep off the construction site.
  • We apologize for noises, dust, vibration, limited parking spaces and detours caused by the construction. Thank you for your cooperation.
  • Construction project will be postponed due to rain or university events.
ContractorDing Shiun Gung Cheng Ltd. 03-59939020937-534696

ContactChe-Yung Wei, Office of General Affairs, Division of Construction and Maintenance 03-5162285 (Campus phone62285)

Emergency Contact for Campus SafetyCampus Security Office 03-5715131 (Campus phone33333)

Click Num:
Login Success