3/5~4/4 Announcement of Recent Schedule for Museum Plumbing Renovation Project
Subject: Underground Pipeline Construction at the Art Gallery to Tsing Hua Laboratory , Vehicle Diversion, and Construction Schedule.
- This construction starts from 2024/03/5 (Tue) to 2024/4/4 (Thu).
- Construction areas are shown on the maps below. Due to the safety reason, non-construction personnel please keep off the construction site. Parking space will be partially limited, vehicles and pedestrians are advised to follow the designated routes.
- We apologize for noises, dust, vibration, limited parking spaces and detours caused by the construction. Thank you for your cooperation.
- Construction project will be postponed due to rain or university events.
Contractor:Hong-Guo Construction Co., Ltd (Mr. Chen: 0931-621683)
Construction Supervisor:Te Chec Engineering Consultants Co., Ltd (Mr. Lim:0922-134676)
Contact:Mr. Wu , Division of Construction and Maintenance 03-5162289
Emergency Contact for Campus Safety:Campus Security Office 03-5715131 (Campus phone:33333)