Annual Maintenance & Inspection Notice for High-Voltage Substations (Nanda Campus, 2026)
Outage Locations and Schedule:
|
Date |
Campus |
Buildings |
Time |
|
Saturday, August 1st. |
Nanda Campus |
General Building |
08:00~12:00 |
|
Administration Building、Instructional Building、Department of Chinese Language and Literature、Department of Environmental and Cultural Resources、Department of Applied Science、Department of Arts and Design、Western Painting Building、Student Activity Center I、Music Building I、Music Building II、Student Activity Center II、Ming-Feng Hall、Ying-Xi Hall、Chong-Shan Hall、Shu-De Hall、Ju-Yue Hall、Library、University Archives、Gymnasium、Yin-Hong Hall |
08:00~17:00 |
||
|
Sunday, the 5th of July. |
Nanda Campus |
Continuing Education Building |
8:00~12:00 |
|
Physical Education and Health Teaching Building |
12:00~17:00 |
Reasons for Outage & Important Instructions
- Annual Maintenance: Scheduled periodic maintenance and safety inspection for all high-voltage substation facilities and equipment across the campus.
- Equipment Safety: During the outage, all departments, institutes, and dormitory units within the affected areas must unplug all computers and laboratory equipment. Please also disconnect power supplies at distribution boards and switch boxes to ensure electrical safety and prevent potential damage from power surges upon restoration.
- Notification & Restoration: In addition to this email, physical notices will be posted at all building entrances and elevator lobbies. If the inspection is completed ahead of schedule, power will be restored early without further notice. We apologize for any inconvenience.
- Estimated Schedule: The end time stated in this notice is an estimate. Actual restoration time will depend on the day's technical progress.
- Contingency Planning: If your unit has scheduled important meetings or activities during this period, please carefully assess the impact and prepare a backup plan or consider rescheduling to avoid disruptions caused by potential adjustments in the work progress or restoration time.
Your cooperation in making early preparations is greatly appreciated.
Maintenance and Construction Group, Office of General Affairs
Contact: Mr. Hsu (Ext. 35253)
Date: March 10, 2026